ROV tooling skid

Mounting inspection and operational equipment

Tooling frame. General view
Purpose

Mounting inspection and operational equipment

The tooling frame carries inspection and operational equipment for ROV surveys of linear subsea assets. The dedicated frame substantially reduces the time needed to reconfigure an ROV for pipeline inspection.

The frame attaches to the ROV using pins and mating sockets provided on the vehicle. The frame includes:

  • Adjustable mounts for multibeam echo-sounder (MBES) transducers.
  • Mounts for additional lighting.
  • Hydraulic inspection arms for cameras and lights.
  • Retractable tool tray.
  • Folding wheel pairs for controlled travel along a pipeline, adjustable to its diameter.
  • Movable pipeline-tracker frame mount made from non-magnetic materials.
  • Subsea hydraulic control equipment.
  • Multiplexer.
  • Dedicated software for controlling the frame components.
PriceOn request
Manufacturing lead timeOn request
Parameters

Technical
specifications

Final configuration and operating conditions are agreed in the technical specification.

ParameterValue
Nominal hydraulic control block pressure, MPa20
Maximum hydraulic control block pressure, MPa25
Pipeline diameters for wheel-pair positioning, inches32, 40, 48
Wheel outside diameter, mm250
Distributed payload on the retractable basket, kg40
Inspection-arm payload, kg, maximum6
Maximum opening angle of the pipeline-tracker antenna mounting system90°
Horizontal adjustment of the inspection-arm pan/tilt platform±90°
Vertical adjustment of the inspection-arm pan/tilt platform±45°
MBES transducer mount extension adjustment, mm0–400
MBES transducer mount tilt adjustment±30° from nominal position
MBES transducer mount angular adjustment increment5°
Data link to the ROV control systemGigabit Ethernet
Data link to equipmentEthernet / RS232 / RS485
External equipment power supplied by the multiplexer24 V DC, 25 A; 48 V DC, 1 A
Operator workstation operating systemWindows / Linux
Ballast element mass, kg, maximum56
Mass in air, kg, maximum1700
Mass in water at maximum ballast and water density of 1000 kg/m³, kg, maximum50
Applications

From task
to operation.

Pipeline inspection

Mounting a pair of inspection boom arms and adjusting wheel pairs to the working geometry.

Operational tasks

Storing and deploying interchangeable tooling on the extendable shelf.

System integration

Combining hydraulic consumers with control from the operator station.